MOSCOW, Nov 27 (Reuters) - Gas giant Gazprom plans to convert some of Russia's idle gas compressor facilities into power plants to help address local power shortages and meet rising demand from data centres, a company executive and an Energy Ministry official said.

Gazprom has identified 400 megawatts of pilot projects to convert compressor stations into power generation facilities, Anatoly Shapovalo, a department head at Gazprom, said on Friday.

The new generating capacity could help offset growing power shortages in southern and central Russia and help meet rising demand from data centres, he said.

In addition to its gas transportation and oil and gas production businesses, Gazprom is one of the country's biggest power plant operators, including assets in the Moscow region, where most of the country's data centres are concentrated.

Part of Gazprom's gas transmission system is currently underutilised. Gas supplies via the Yamal-Europe pipeline and Nord Stream were halted after the start of the Russia-Ukraine conflict, while the transit of Russian gas via Ukraine has been halted since the start of last year.

The loss of the European market has forced Russia to seek additional domestic consumers for its gas.

Converting existing facilities would allow new generating capacity to be commissioned more quickly and at lower cost than building power plants from scratch, Shapovalo said.

Elena Medvedeva, head of an Energy Ministry department, said the government could designate Gazprom to implement the project under a mechanism already used in regions where power is short, and where investors were reluctant to bid for new generation projects because of profitability risks.

She estimated the conversion of compressor units could take about 18 months.

Gazprom is already among investors designated by the government to build new generating capacity in the potentially power-short Moscow region and southern Russia.

Earlier this week, Russian President Vladimir Putin proposed developing a public-private partnership framework to accelerate data-centre construction and integrate new facilities with existing power plants. He has previously called for data centres to be built near nuclear power plants and coal and gas fields.

According to an Energy Ministry estimate released in September, power demand from data centres could triple by 2030 to 15 gigawatt.

(Reporting by Oksana Kobzeva and Anastasia Lyrchikova. Editing by Susan Fenton)

Find it fast

Looking for more insights? Explore our other news sections for updates on sustainable finance, companies and financial education